Prospect Avenue Project Moving Ahead

Monday, March 30, 2015


Decorative pedestrian crossing at Cottonwood Ave.
Expect a bustle of activity in the “cone zone” along Prospect Avenue this week.
On Wednesday, April 1, pavement work will be occurring at the western end of Prospect between Railroad and North Magnolia avenues, the last major section of asphalt to be removed and replaced.

On Thursday, April 2, traffic lanes between Railroad and North Magnolia avenues will be re-routed to the outside lanes to allow workers to remove the center lane, which will be rebuilt.  For the duration of this work, turns across the construction zone will not be allowed. However, motorists can access businesses on the opposite side of the street by taking a U-turn at either Railroad or North Magnolia avenues.
The repaving of Hacienda Road on the north side of Prospect has been scheduled to begin in the next two weeks.  Flyers detailing the construction schedule will be distributed to residents.

A decorative sidewalk similar to the one recently installed at Cottonwood Avenue will be under construction at the North Magnolia Avenue intersection.

Workers this week will be installing street lights, installing electrical conduit  and equipment at businesses and residents to convert the overhead wires to an underground system.  Contractors will also be pouring concrete driveways and curbs throughout the project area, which stretches for a mile between Cuyamaca Street and North Magnolia Avenue.
Questions or comments about the project can be directed to Senior Civil Engineer Toby Espinola at  (619) 258-4100 ext. 174.

 