Prospect Avenue Enhancement Update

Tuesday, March 25, 2014


April 25, 2014
Installation of storm drain pipes continues this week, while workers install curb inlets and catch basins (places for storm water to drain) on the south side of Prospect.
Contractors will continue digging trenches between Cottonwood and Magnolia avenues to install conduit that will allow overhead wires to be placed underground.

SDG&E crews are continuing with their work lowering natural gas laterals – connections from the main line to adjoining buildings – to accommodate the new storm drains.
A new retaining wall is taking shape near Magnolia Avenue.

Work days and hours will continue to be Monday through Saturday from 6 a.m. to 6  p.m.
Project manager Toby Espinola urges motorists to observe the 25 m.p.h. speed limit in the construction cone zone.  Espinola can be reached at (619) 258-4100 ext. 174.