The first two of seven structures slated for removal were demolished last week.
This week, the project passed the 50-day mark as workers
began installing underground conduit that will replace unsightly overhead
electrical wires. Work started near Cottonwood Avenue and will move east toward
Magnolia Avenue.
Meanwhile, SDG&E
is moving natural gas lines to accommodate the new storm drain system. Work
days and hours will be 6 a.m. to 6 p.m. Monday through Saturday.
Motorists should heed the 25 m.p.h. speed limit within the “cone
zone,” and remember that traffic fines are double inside construction zones.
Questions or concerns about the project can be directed to Senior
Civil Engineer Toby Espinola at (619) 258-4100 ext. 174.