/*added another slider news box below here*/

Monday, August 3, 2015

Work Started on Citywide Pavement Repair Project

Monday, August 3, 2015

 

Work has begun on a $4 million citywide street improvement project that will upgrade pavement, curbs, gutters and sidewalks in five neighborhoods.

The project, which is funded through the Sandag Transnet program, began July 20 and will be completed in four to five months.

The city’s subcontractor, YBS Concrete, is currently working in the Settle Road area, where asphalt patching is set to begin August 17 and finish in five days. Earlier this year, a crack seal was applied to the road to prevent further damage.

 Final resurfacing of Settle Road and adjacent streets will be scheduled after the asphalt repair work is completed.  Next up: Concrete replacement along Strathmore Drive is scheduled to start August 10.

“No Parking” signs will be placed 48 hours in advance at locations where curb, gutter or sidewalk work is scheduled.

 Workers are currently identifying the locations of utility lines in advance of storm drain replacement work planned for Alphonse Street, Princess Joann Road and Ironwood.

We’ve included (below) a map of the streets and neighborhoods that comprise the project.  

Questions or feedback can be directed to Senior Civil Engineer Toby Espinola at (619) 258-4100 x 174 or via email at tobyespinola@CityofSanteeCA.gov

Curb and gutter and sidewalk work on Settle Road
 

 

 
 



 

Post a Comment

Note: Only a member of this blog may post a comment.