Final paving of Prospect Avenue and the intersections at
Magnolia Avenue and Cuyamaca Street has been completed except for areas where the
old power poles need to be removed.
Telephone, power and cable companies are installing cable and wire into conduits
below the surface, the next step toward converting overhead wires to the new underground
system. The conversion work will be performed and coordinated with property
owners by SDG&E, Cox and AT&T.
Once the utility and cable companies have converted all
properties to the underground system, the overhead wires and the wood
power poles holding them up will be removed.
Asphalt and concrete near the old power poles will be
replaced once the poles are gone.
The new LED street lights will be turned on in segments as the
power system is undergrounded.