Prospect Avenue Enhancement Update

Wednesday, June 17, 2015


Final paving of Prospect Avenue and the intersections at Magnolia Avenue and Cuyamaca Street has been completed except for areas where the old power poles need to be removed.

Telephone, power and cable companies are installing cable and wire into conduits below the surface, the next step toward converting  overhead wires to the new underground system.   The conversion work will be performed and coordinated with property owners by SDG&E, Cox and AT&T.
 
Once the utility and cable companies have converted all properties to the underground system, the overhead wires and the wood power poles holding them up will be removed.

Asphalt and concrete near the old power poles will be replaced once the poles are gone.

The new LED street lights will be turned on in segments as the power system is undergrounded.