Wednesday, July 9, 2014
Prospect Ave Corridor Enhancement Project Update for July
Wednesday, July 9, 2014
Work will continue on the installation of the electrical
conduit to convert the overhead electric line to an underground system.
Miscellaneous storm drain structures, such as curb inlets
and catch basins will continue along Prospect Avenue.
Fire hydrants and water services are being relocated to the
new right of way location.
Three more structures will be demolished during the week of July
14.
Concrete driveways have started to be formed and
poured. Please avoid driving and walking on the fresh concrete to allow
the concrete driveway to properly cure.
Work days and hours will be Monday through Saturday from 6 a.m.
to 6 p.m.
Please observe the 25 m.p.h. speed limit within the
construction zones. Traffic fines will be doubled within the construction
zone.
If
you have any project related questions, please feel free to contact Toby
Espinola, P.E., City of Santee, 619-258-410