Storm drain work |
This week we’re installing more electrical conduit so we can
underground overhead electric wires. This work will continue east of Cottonwood
Avenue.
We’re also installing storm drain structures called curb inlets and catch basins on the south side of Prospect Avenue.
There’s also work being done on a retaining wall near
Magnolia Avenue.
SDG&E is lowering gas pipes to allow us to install the
new storm drain system.
The third of seven structures slated for demolition has been
completed near Magnolia Avenue.
Please observe the 25 mph speed limit within the
construction cone zone, where traffic fines are subject to being doubled.
Questions? Contact senior civil engineer Toby Espinola at
619-258-4100 x 174.