Carlton Hills Blvd.
All concrete repair work has been completed and pedestrian ramps have been installed at each street intersection in advance of the storm drain and pavement repairs.
The next phase of work after the concrete work will be the replacement of storm drains along Carlton Hills Blvd. During utility conflict investigation for the storm drain construction, two conflicts were discovered at waterline crossings that had very minimal clearance. Padre Dam Municipal Water District is currently working on lowering the waterlines to avoid the conflict. The waterline work will begin during the week of February 27.
After the waterline relocations and storm drain replacement work is completed, asphalt patching and a final asphalt overlay will be completed on the entire length of Carlton Hills Blvd.
Construction schedule dates will be updated as construction progresses on each phase of work on Carlton Hills Blvd.
If you have any questions, please contact Toby Espinola, P.E., City Project Manager at (619) 258-4100 x 174.
Wednesday, February 8, 2012
City Wide Paving Project Update
Wednesday, February 8, 2012
Labels:
Construction Update,
Streets
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment