/*added another slider news box below here*/

Friday, October 21, 2011

City Wide Paving Project Update

Friday, October 21, 2011

East Glendon Circle Neighborhood
The asphalt overlay has been completed with final striping to be scheduled.

Rumson Drive
Due to the asphalt plant being repaired, the asphalt overlay has been scheduled for October 21 and 24.  Speed humps will be replaced on Rumson Drive once the asphalt overlay has been completed.

Mission Gorge Road
All concrete replacement work has been completed with asphalt patching to begin on Sunday, October 30.  Night work hours will be from 9:00 p.m. to 5:00 a.m.

If you have any questions, please contact Toby Espinola, P.E., City Project Manager at (619) 258-4100 x 174.