Fanita Parkway |
East Glendon Circle Neighborhood
Isolated areas of patching will occur the week of September 19. No parking signs will be placed near the patching areas.
The final asphalt overlay is scheduled for Wednesday, October 12. No vehicle access will be available during the day. Construction hours will be from 8:00 a.m. to 5:00 p.m. Parking will be available on Magnolia Avenue and El Nopal Drive. Residents who require their vehicles during the construction hours are advised to move their vehicles to Magnolia Avenue or El Nopal Drive prior to the start of construction. Unforeseen emergencies can be accommodated or assistance to and from residences will be available. If you need assistance or have any questions, please contact Toby Espinola at (619) 572-6996.
Lake Canyon Road |
Lake Canyon Road
Lake Canyon Road has been completed with speed humps scheduled to be installed during the week of September 19. One set of speed humps will be relocated near Lake Canyon Court. These two locations of speed humps will have no parking signs installed 48 hours in advance. Striping will be completed shortly after the speed humps have been constructed.Rumson Drive
Concrete construction work will be completed by September 19. Asphalt patching will begin on Rumson Drive starting on September 19. Areas of patching will have no parking signs placed 48 hours in advance.
If you have any questions, please contact Toby Espinola, P.E., City Project Manager, at (619) 258-4100 x 174.
No comments:
Post a Comment