The City of Santee held a preconstruction meeting with the paving contractor, Hazard Construction, on July 19, 2011. A tentative schedule for each neighborhood and street within the project is as follows:
- Fanita Parkway – August 1 to September 1
- Lake Canyon Rd – August 8 to September 1
- East Glendon Rd Neighborhood – August 15 to September 16
- Rumson Drive – August 22 to September 7
- Carlton Hills Blvd – August 15 to November 18
- Mission Gorge Rd – November 7 to November 23
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjtbD5kyiIrhUxg0xkpZBd3raj_9H-DESQ07IjdnyJEZhKdEAlRdoCMXgcj4o-NLYXGcaoH5mG9FeNvBMhdiZrDrI1M2vEmG8PL-rwrSX19s8ALliF0fUQ_OO5OFnwR-wJPbYVJZabgI2Sm/s320/6.jpg)
Construction updates and revised schedules will be posted on the City’s website as construction progresses.
If you have any questions, please contact Toby Espinola, City Project Manager, at (619) 258-4100 x 174.