Santee Street Repair Update

Wednesday, May 23, 2012

Carlton Hills Boulevard

Watch for traffic cones and lane closures along Carlton Hills Boulevard
beginning May 29.

City contractors will be replacing corrugated metal storm drains at 5 locations along Carlton Hills Boulevard, starting at the northern terminus and working south towards Mission Gorge Road.
Storm drain construction will occur from to Monday through Friday, is expected to last about 2 ½ months.

Once the storm drain is completed, look for updates concerning asphalt patching and a final asphalt overlay for Carlton Hills Boulevard.

Mission Gorge Road


An asphalt overlay project along Mission Gorge
Road between Cottonwood Avenue and Civic Center Drive
is scheduled to start the week of June 18.

To minimize any inconvenience to motorists, the work will take place overnight between and

Project manager Toby Espinola can answer questions at (619) 258-4100 ext. 174